Problem Summary
The report which is scheduled to run at 7 am is failing at a random interval. Need to be investigated and fixed.
Admin Info
Purpose
|
The report which is scheduled to run at 7 am is failing at a random interval. Need to be investigated and fixed.
|
Requested by
|
Kris Paxson
|
Issue Date
|
02-21-2014
|
Resolved by
|
Praveen Guntuka
|
Resolved Date
|
02-22-2014
|
Document Status
|
Complete
|
Detailed Problem Description
Getting below error intermittently for WMS250report:
Solution Analysis and Recommendations
1. The report was failing due to server overload.
2. Need to schedule the report in different time.
Resolution
Need to schedule the report in different time.